Category: extension (Page 4 of 4)

More progress on the blockwork

Although the work is still to start on the exterior wall of the extension, the internal blockwork seems to be shooting up.  In much of the extension we are up to ceiling level.  We can build up into the gables, but by the end of the week much of the blockwork will be complete.

As the walls go up, the thing that is most striking is the height of the rooms inside.  This makes this space feel very open.

As the walls go up, the thing that is most striking is the height of the rooms inside. This makes this space feel very open.

Despite the showery weather we are making good progress on the blockwork for the extension.

Despite the showery weather we are making good progress on the blockwork for the extension.

The large brown pipe protruding from the wall is the air intake for the log burning stove that will be installed in the lounge.

The large brown pipe protruding from the wall is the air intake for the log burning stove that will be installed in the lounge.

You can see part of the dry stone wall in the courtyard garden in the foreground.

You can see part of the dry stone wall in the courtyard garden in the foreground.

There is a large square opening between the lounge and the kitchen.  A large oak truss will sit on top of this wall supporting the roof.

There is a large square opening between the lounge and the kitchen. A large oak truss will sit on top of this wall supporting the roof.

More reclaimed stone arrives

Our 2nd of three loads of reclaimed stone for the exterior of the extension arrived late this afternoon.  This makes a total of 140 sqm on site.  Tomorrow, this stone will need to be coursed out.  A job that can apparently be done in the rain. This is just as well as the forecast for tomorrow is for showers!

Another 70 sqm of reclaimed stone arrived today.  This is the 2nd load of three.  Tomorrow, it will need to be coursed out.

Another 70 sqm of reclaimed stone arrived today. This is the 2nd load of three. Tomorrow, it will need to be coursed out.

When this stone has been coursed out, it will be sorted into the same piles that you can see in the background.

When this stone has been coursed out, it will be sorted into the same piles that you can see in the background.

Progress on the extension

Work continues on the blockwork and there are probably 3-4 days left before we reach roof level.

The reclaimed stone that is going to be used for the exterior skin turned up right at the end of the day.  The first job will be to “course out” the stone  – sorting it according to the height of the stone.  Stones of the same height will be used to make up the courses with the larger stones at the bottom and the smaller stones at the top.

This is going to be time-consuming process.  In the meantime, the work will continue on the blockwork.  The other factor here is the weather – it is possible to put up the blockwork in the rain, but not the reclaimed stone (the rain can wash the mortar down the front of the stones).  The weather forecast for the rest of the week is “mixed”.

There are another 3-4 courses of blocks to go before we reach roof height.  The reclaimed stone for the exterior skin arrived this evening - well the first batch anyway.  The exterior wall is going to be a lot slower than the blockwork.

There are another 3-4 courses of blocks to go before we reach roof height. The reclaimed stone for the exterior skin arrived this evening – well the first batch anyway. The exterior wall is going to be a lot slower than the blockwork.

At this rate, we will have a large proportion of the blockwork completed before the end of the week.

At this rate, we will have a large proportion of the blockwork completed before the end of the week.

We can't go any further with the internal wall in the kitchen as the interior wall is made up of re-used stone that we have reclaimed during the demolition. The bi-folding doors are on order.

We can’t go any further with the internal wall in the kitchen as the interior wall is made up of re-used stone that we have reclaimed during the demolition. The bi-folding doors are on order.

70 square metres of reclaimed stone.  This is the first of three loads.  It will be used for the exterior wall on the extension.

70 square metres of reclaimed stone. This is the first of three loads. It will be used for the exterior wall on the extension.

These are one tonne bags that have more than a tonne in them.  No prizes for guessing what happens!

These are one tonne bags that have more than a tonne in them. No prizes for guessing what happens!

More blockwork

We are three days in and the blockwork in the new extension is already around shoulder height.  We are expecting the first load of reclaimed stone to arrive on Friday and in the between we have been concentrating on blockwork.  Blocks go up much quicker than stone!

For the past few weeks we have been able to wander around the extension without worrying about the walls.  Now, we can only walk around the extension by using the door openings.  This has taken a little while to get used to!

You can see the land drain in the bottom of the retaining wall as well as the damp proof course on the side of the extension.  The manhole to camera right houses one of the three manifolds for the ground loops for the underfloor heating.

You can see the land drain in the bottom of the retaining wall as well as the damp proof course on the side of the extension. The manhole to camera right houses one of the three manifolds for the ground loops for the underfloor heating.

We are three days in and the blockwork is around shoulder height.  It has already got to a point where we can only walk around the extension by using the door openings.

We are three days in and the blockwork is around shoulder height. It has already got to a point where we can only walk around the extension by using the door openings.

There is a damp proof course (the black plastic) around this part of the building as the ground level outside is above the floor level inside the extension.

There is a damp proof course (the black plastic) around this part of the building as the ground level outside is above the floor level inside the extension.

Blockwork in the new extension

We started putting up the blockwork in the new extension today.  We have placed an order for the reclaimed stone that will be used for the exterior.  It should be delivered (or rather the first consignment) midweek this week. In the meantime, we will continue with the blockwork.

The first task is to bring all of the blockwork walls up to the same level.  This isn’t easy as there are multiple levels in the extension.  Once the walls are all up to the same level, it should go up very quickly.  That is the theory anyway!

It already feels different with a couple of courses of blockwork.  Strangely, it feels bigger with the blockwork down.

We have started on the blockwork for the extension today.  The reclaimed stone for the external walls arrives midweek, until then we will continue work on the blockwork.

We have started on the blockwork for the extension today. The reclaimed stone for the external walls arrives midweek, until then we will continue work on the blockwork.

We have spent most of the day getting all of the walls in the new extension up to the same level.  This means using some bricks on some of the walls.  Once we have all the walls to the same level, it is much quicker to then build the rest of the blockwork.

We have spent most of the day getting all of the walls in the new extension up to the same level. This means using some bricks on some of the walls. Once we have all the walls to the same level, it is much quicker to then build the rest of the blockwork.

Newer posts »

© 2025 Hagg Leys Farm

Theme by Anders NorenUp ↑