We have plastered about 75% of the older part of the property and have started plastering the new extension. This week we have plastered the two ensuites, the dressing room and the master bedroom. With this much plastering, the building can get damp very quickly – plastering the walls in wet plaster introduces a lot of water in the building. Although the ground source heat pump is up and running, we have also left a dehumidifer running to accelerate the drying process.
Next week we will make a start on plastering the kitchen. My guess is that it will take most of the week to get the ktichen plastered.