Progress on the home automation

While work is progressing on the first fix electrics in the extension, we are starting to terminate the cables for the lighting switches.  All of the cables of the lighting and data will terminate in patch panel.  This allows us to easily test all of the connectivity as well as being able to reconfigure the cabling at a later data.

There are 19 lighting switches in the older part of the building.  The cables will terminate in a single 24 port patch panel.  Patch leads will then connect the relevant port to the correct connection on the lighting computer.

The data connections will terminate in two 24 port patch panels since there are more than 24 data connections in this part of the building.  These will be connected to a Netgear network switch that will be connected to the broadband route to provide wired Internet access into each of the rooms.  There will be a second Netgear switch in the extension and the two switches will be connected together.

It will probably take a few days to get all of this connectivity working!

The top two consumer units house the Loxone kit - a server, 2 extensions and a dimmer unti.  The bottom consumer unit contains the breakers and RCD.  Underneath this there is a small data comms cabinet.

The top two consumer units house the Loxone kit – a server, 2 extensions and a dimmer unti. The bottom consumer unit contains the breakers and RCD. Underneath this there is a small data comms cabinet.

All of the Cat5 cables from the lighting switches terminate in this patch panel.  There are 19 in this half of the building.  There will then be a lead from the patch panel to the Loxone lighting computer which is housed above.

All of the Cat5 cables from the lighting switches terminate in this patch panel. There are 19 in this half of the building. There will then be a lead from the patch panel to the Loxone lighting computer which is housed above.

Second fix electrics

We are getting ready for the second fix electrics.  The new three-phase supply is due to be installed next week, so there is a lot of work to do.

We need to put a three-phase distribution board in the extension and then connect this to a consumer unit in the older part of the building.  This means that there are essentially two consumer units in the property enabling us to shut off the power separately in the two parts of the building. 

The plan is to get these consumer units in place for when the new power supply is connected.  If we don’t do this, we won’t have any power next week.

We are also installing the Loxone kit that will control the lighting, heating and some of the other features.  There will be Loxone kit in both the new extension and the renovated part of the building.  The mini-server will be installed in the renovated part and a number of extension modules will be installed in the extension.  The Loxone kit is being housed in standard consumer units – there are relatively inexpensive and easy to source.

This is still work in progress and I reckon we won’t have this powered up until the middle of next week.

The new supply comes into a meter box on the opposite side of this wall.  A cable will then come through the wall and feed this consumer unit.  There is a feed from here to a second consumer unit in the renovated part of the property as well as a feed to the shed.

The new supply comes into a meter box on the opposite side of this wall. A cable will then come through the wall and feed this consumer unit. There is a feed from here to a second consumer unit in the renovated part of the property as well as a feed to the shed.

The top two consumer untis will house the Loxone kit.  The bottom unit houses the breakers and RCDs.

The top two consumer untis will house the Loxone kit. The bottom unit houses the breakers and RCDs.