Category: floors (Page 3 of 3)

The flooring for the first floor has arrived!

All of the timber for the first floor was removed when we gutted the property.  The existing timbers were either rotten, had holes cut in them all over, or were just bent.  This meant that the existing first floor undulated, particularly in number 8.  We took the decision early on to replace all the timber.

The timber for the new first floor arrived today.  There are 6 green oak beams that make up the first floor.  Two beams in each cottage.  These beams are very heavy.

Then there are joists that run from the beams to the walls.  The floor deck is tongue and groove chipboard.

Made from green oak.  These beams are seriously heavy!

Made from green oak. These beams are seriously heavy!

New kitchen floor

8am Saturday morning and we have turned a corner – we have started to put things back.  This morning the new kitchen floor arrived in a concrete mixer.  3.5 cubic meters.  This is enough for the new kitchen floor as well as for the footings for the re-built outbuilding.

Unfortunately, it wasn’t possible to be able to shoot it straight from the cement mixer into the kitchen, so it had to be dumped on the tarmac and moved by hand. All in all, it took a couple of hours to sort out the footings as well as laying the floor.

Unfortunately we couldn't shoot it in directly from the mixer so it was offloaded onto the tarmac and then barrowed in.

Unfortunately we couldn’t shoot it in directly from the mixer so it was offloaded onto the tarmac and then barrowed in.

It couldn't be shot straight off the mixer into the kitchen, so 3.5 cubic meters of concrete was dumped on the tarmac.  It was then a case of using shovels and wheelbarrows.

It couldn’t be shot straight off the mixer into the kitchen, so 3.5 cubic meters of concrete was dumped on the tarmac. It was then a case of using shovels and wheelbarrows.

Damproof course and steel mesh laid ready for the concrete.  Notice the old doorway that has been bricked up in the background.

Damp proof course and steel mesh laid ready for the concrete. Notice the old doorway that has been bricked up in the background.

Ready for the concrete.  The doorway has moved in this room - the old one was bricked up and a new one cut.

Ready for the concrete. The doorway has moved in this room – the old one was bricked up and a new one cut.

It only took a couple of hours to lay the new concrete floor in number 10.  The black plastic is the damp proof course that is laid underneath the concrete.

It only took a couple of hours to lay the new concrete floor in number 10. The black plastic is the damp proof course that is laid underneath the concrete.

Flagstone floors

All three cottages have flagstone floors.  At some point, all of the cottages have had a layer of asphalt laid over the flagstones.  Presumably, this was to prevent the damp coming through the flagstones – the stone itself is porous.  Although the asphalt is still in place in number 8 and (what was) number 9, the asphalt had been lifted in number 10.  There were remnants of the asphalt floor under the kitchen units and under the stairs.

We are still working out what to do with the floors.  There are two main issues to be dealt with:

  • The flagstones are porous and are laid directly onto the earth below.  This means that the floor is prone to be damp;
  • There are cellars in number 8 and (what used to be) number 9.  The ceiling of the cellars is made up of 6ft x 4ft stone slabs.  Normally, the damp would be treated by digging up the floor and laying a waterproof concrete floor.  However, this isn’t possible because of the stone slabs over the cellar.

Following the architect’s advice,  I pulled up one of the smaller stone flagstones and had a look underneath.  I took up one of the flagstones that was against the wall, so that we can see the extent of the foundations.  The flagstone is laid directly onto the soil.  The soil is about 12 inches deep on top of (what looks like) bedrock.

Looking on the outside of the wall, the foundation stones are exposed at the base of the wall.  Originally, the ground level outside of the kitchen was just below the level of the current window cill, however, it was dug out when the garden was landscaped and the conservatory (now removed) was built.

Pulling up the flagstone confirms what we thought – they are laid directly onto the earth below.  This explains the dampness coming through the flagstones.  However, it also seems to indicate (at least in this part of the building) that the foundation stones are laid directly onto the bedrock below.

Let’s see what the architect has to say later in the week.

I took up one of the flagstones next to the wall.  While the stone is laid directly onto the earth below, it is only 6 inches deep as there is bedrock below.

I took up one of the flagstones next to the wall. While the stone is laid directly onto the earth below, it is only 6 inches deep as there is bedrock below.

The ground level used to be just underneath the window cill, but was dug out when the back garden was revamped.  You can see the foundation stones at the base of the wall.  The flagstone that we have pulled up is directly the other side of the wall.

The ground level used to be just underneath the window cill, but was dug out when the back garden was revamped. You can see the foundation stones at the base of the wall. The flagstone that we have pulled up is directly the other side of the wall.

Newer posts »

© 2024 Hagg Leys Farm

Theme by Anders NorenUp ↑