We have made some good progress today.  The concrete floors in the extension have been laid.  The concrete was poured first thing this morning and by “going home” time it was possible to walk on it.

We have also finished excavating the land for the ground loops.  This is just as well since we seem to be running out of space to put all of the spoil.  Tomorrow we will put down sand on the base of the area and on Thursday, we will install a 1000m of pipework for the ground loops.  We aren’t entirely sure if we have the space, but we will only find out when we try.  Let’s see what happens later in the week.

We started pouring the concrete first thing this morning and by close of business we could walk on it.

We started pouring the concrete first thing this morning and by close of business we could walk on it.

Tomorrow we need to put around 60 tonnes of sand on the bottom of this patch of land before installing the ground loops for the ground source heat pump on Thursday.

Tomorrow we need to put around 60 tonnes of sand on the bottom of this patch of land before installing the ground loops for the ground source heat pump on Thursday.