Tag: demolition

Demolishing another wall

One of the internal walls has had to come down. It already had a couple of bricked up doorways in it and trying to make two new doorways just introduced the risk that it was going to destabilise the wall.  The decision was taken earlier in the week to take it down and replace it with blockwork.  By Wednesday, the new wall had started to re-appear.  Fingers crossed, it will be finished this week.  While the wall is being re-built, the roof is being propped up.  This saves having to dismantle the roof, but it does look a little precarious.

The stone from the wall is very similar (if not identical) to the other internal wall that we had to remove last week.  It is likely that this stone will be reused on one of the internal walls in the kitchen (when that is built as part of phase 2).  So the mound of stone in the back field just grows bigger.

The start of a new wall between number 9 and number 10 - there were just too many alterations in the existing wall for it to be safe.

The start of a new wall between number 9 and number 10 – there were just too many alterations in the existing wall for it to be safe.

The new wall seen from the other direction.  Zep conducts his daily inspection of the building once the builders have gone home (looking for any leftover pasties!).  Note the tie beam on the king post truss in the background (the big beam running horizontally).  This is going to be replaced as part of the renovation.  The carpenter tells me that he thinks that this beam is original.

The new wall seen from the other direction. Zep conducts his daily inspection of the building once the builders have gone home (looking for any leftover pasties!). Note the tie beam on the king post truss in the background (the big beam running horizontally). This is going to be replaced as part of the renovation. The carpenter tells me that he thinks that this beam is original.

some of the best stone that we have found so far.  Fairly square and pretty regular.  We wll probably use this for the internal wall in the kitchen as part of the phase 2 build.

some of the best stone that we have found so far. Fairly square and pretty regular. We wll probably use this for the internal wall in the kitchen as part of the phase 2 build.

Outbuilding gone…….

…..and the footings dug.  We need the building inspector to give it the OK tomorrow and then the footings will be laid on Friday.  Work will then start early next week rebuilding it, but this time with a proper cavity wall and a concrete slab floor (rather than flagstones laid directly onto the earth below).  It will be great to start building things rather than just knocking them down!  I can’t wait.

Walls removed and the footings dug ready for the concrete on Friday.

Walls removed and the footings dug ready for the concrete on Friday.

The walls now have been completely removed and the footings dug.  Once the wall has been built up to ground level, the soil and debris from the centre will be used to backfill the rest of the trench.

The walls now have been completely removed and the footings dug. Once the wall has been built up to ground level, the soil and debris from the centre will be used to backfill the rest of the trench.

Oops! We need to get this replaced, but we will reattach the plate to the wall once re-built as a temporary measure.

Oops! We need to get this replaced, but we will reattach the plate to the wall once re-built as a temporary measure. It used to be against the wall along the road.  When the wall was removed, so was this.

The stone from the outbuilding

The stone from the outbuilding

Outbuilding almost gone

Well, the weather has been fantastic and the builders have really made some progress taking the outbuilding down at the end of the building.  With any luck  the new footings and floor will be exacavated tomorrow.  Within a few days, the rebuilding of this outbuilding will start.  This will be a real turning point as we start to put the building back together.

It has only taken the builders two days to get this far in demolishing the outbuilding at the end of the property.

It has only taken the builders two days to get this far in demolishing the outbuilding at the end of the property.

Outbuilding being demolished..

…to then be rebuilt.

Unfortunately, this is a single skin building with flagstones that are laid directly onto the soil.  As such, it is susceptible to damp and the only real solution is to take it down and rebuild it with a proper concrete floor and a cavity wall.  From the outside, it will look very similar to the building as it currently is, but it will be of a solid modern construction.  It will have been completely removed in the next two days.

At the end of day one, the roof has gone and the main roof timbers are exposed.  Work has already started on removing the stone work.  This is put onto pallets so they can be easily moved around the site.

This seems like a lot of trouble to go to for a quirky room on the end of the building, however, the 1788 map shows that this room was here back then.  So we would like to keep it in place. Longer term, it is going to be my office space.

The roof has been removed and the stones blocks are being removed one at a time.

The roof has been removed and the stones blocks are being removed one at a time.

© 2024 Hagg Leys Farm

Theme by Anders NorenUp ↑