Tag: roof

Starting on Phase 2

The first phase of construction work (the renovation of the existing cottages) is drawing to a close.  I reckon we will be complete in the next 2-3 weeks.  This means that some of the men are coming free from the existing building work.  Although the architects are still working on the detailed design for phase 2 (the build of the new extension), we have decided that we can start on the demolition of the existing barn and laying down the new concrete base.  This should provide the architects with a little more time to finalise the overall design – the concrete base is not going to change (well, not without having to go back to the Planning department).

The roofline of the new extension will be slightly below the existing roofline.  This means that part of the gable end will be exposed.  This means that we need to hack of the existing render and either re-point the stonework or render the gable end. 

As part of the phase 2 work, the barn will be demolished and rebuilt.

As part of the phase 2 work, the barn will be demolished and rebuilt.

The roof line of the new extension is going to be lower than the existing roofline.  This means that part of the gable end (that is currently rendered) is going to be exposed.  We need to remove the rendering to check the quality of the underlying stone.

The roof line of the new extension is going to be lower than the existing roofline. This means that part of the gable end (that is currently rendered) is going to be exposed. We need to remove the rendering to check the quality of the underlying stone.

Progress with the roof and extension

We are making good progress this week with both the roof and rebuilding the extension.

While the weather has been good, attention has been turned to rebuilding the extension.  We can’t progress with the pointing until we have had the go ahead from the architect on the choice of materials.  We have completed a test panel for approval using Nosterfield River sand and hydraulic lime, but this needs a little bit of time to dry out so we can see the true colour.

It could a couple of days to completely felt and lathe the roof.  However, today work started on relaying the slates.  Five courses are on at the rear of the house.  Slightly less at the front, due to the rooflights having to be fitted as well.  We have had to buy some additional slates to make up for the ones that were damaged or too aged to be reused.

Concrete blockwork on the inside then 100mm insulation and finally the original gritstone on the outside.  Once it is finihsed, we will get it sandblasted to match the main property.

Concrete blockwork on the inside then 100mm insulation and finally the original gritstone on the outside. Once it is finihsed, we will get it sandblasted to match the main property.

This is the view of the front of the roof with the two rooflights.  We are waiting for some lead before the slates can be fitted underneath each of the rooflights.

This is the view of the front of the roof with the two rooflights. We are waiting for some lead before the slates can be fitted underneath each of the rooflights.

We had to change the size of the rooflights so that they would sit between the purlins underneath.  These are conservation windows from a company called Fakro (did you guess?).  They are pine on the inside, but will be painted to match the ceiling colour.

We had to change the size of the rooflights so that they would sit between the purlins underneath. These are conservation windows from a company called Fakro (did you guess?). They are pine on the inside, but will be painted to match the ceiling colour.

Five courses of slates on the back of the roof and the two re-built chimneys. This is day 3 for putting the roof back on.

Five courses of slates on the back of the roof and the two re-built chimneys. This is day 3 for putting the roof back on.

Roof going back on

Work started this morning on putting the roof back on the existing building.  By the end of the day all of the roofing felt and lathes will be on the building.  This is a milestone since from this point onwards the building is no longer completely open to the elements.

It will take 7-10 days to get the roof completely finished, assuming there aren’t any problems.

You can also see the two rebuilt chimneys that now match – before the chimney on the left was smaller, rendered and had no string course.  The chimneys, as the rest of the external masonry, has been sandblasted over the last weekend.

 

The two chimneys have been rebuilt and sandblasted.  So too has the rear of the property.  The felt and lathes are going on first to be followed by the stone slates.

The two chimneys have been rebuilt and sandblasted. So too has the rear of the property. The felt and lathes are going on first to be followed by the stone slates.

End of day 1 on the roof and the felt and lathes have been installed.  This means that the worst of the weather will be kept out.  There is still a chance that rain may come through some of the window openings, but fingers crossed the weather shouldn't be too bad for the next couple of weeks.

End of day 1 on the roof and the felt and lathes have been installed. This means that the worst of the weather will be kept out. There is still a chance that rain may come through some of the window openings, but fingers crossed the weather shouldn’t be too bad for the next couple of weeks.

The "felt" is actually a green coloured plastic.  It feels a little bit like a tent wit only the felt and lathes on the roof. With the green felt on the roof, there is a green tinge to the light everywhere.

The “felt” is actually a green coloured plastic. It feels a little bit like a tent wit only the felt and lathes on the roof. With the green felt on the roof, there is a green tinge to the light everywhere.

Installing the roof lights

Unfortunately, the roof lights specified in the drawings are not going to fit – they are just too big for the opening.  We have managed to located an alternative supplier who can provide slightly smaller roof lights.  These are a standard size, so fingers crossed there should be no problems with availability.

There was a slight issue with roof lights as the size specify by the architect was too big to fit.  Slight recalculation and a slightly smaller size has been identified.  The rafters have now been cut to fit the new size roof lights.  These will be the roof lights into Jo's office.

There was a slight issue with roof lights as the size specify by the architect was too big to fit. Slight recalculation and a slightly smaller size has been identified. The rafters have now been cut to fit the new size roof lights. These will be the roof lights into Jo’s office.

Replacing a tie beam

The tie beam in what would have been number 9 needs to be replaced.  Although it is original, it doesn’t match the others and it is much smaller, particularly at the one end.  We weren’t sure if it was original, but the carpenter tells me that it definitely is. It is effectively an old oak tree that has been straightened a bit, but is definitely smaller at one end than the other.  Presumably, the smaller end being the top of the tree.

King post truss in number 9

King post truss in number 9.  The tie beam is the large horizontal beam at the bottom of the truss.

 

This is the old kitchen (downstairs) and bathroom (upstairs) in number 10.  You can just see the king post truss in the top left corner for number 10, and through the upstairs doorway you can see the king post truss for number 9.

This is the old kitchen (downstairs) and bathroom (upstairs) in number 10. You can just see the king post truss in the top left corner for number 10, and through the upstairs doorway you can see the king post truss for number 9.

We have acquired a reclaimed beam to replace it. The timber came from Ribble Reclamation (http://www.ribble-reclamation.co.uk/) in Preston who had a large range of oak beams in stock.  We believe that this particular piece of oak came from France.

The initial plan was to take the roof apart and lift the king post truss out of the roof and to repair at ground level.  Andy, the carpenter, came up with a better way.

The first step is to install a temporary tie beam above the existing one.  This is simply bolted through the existing frame.  Once this is in place, the existing tie beam can be removed.  The simplest way to do this is to cut it into pieces.  However, the existing tie beam is going to be used as a pattern to make the new tie beam from, so it is much better to keep it in one piece. 

In one case, Andy removed the bricks from underneath each end of the tie beam allowing the beam to drop out of each of the tenon joints.  The beam was then slid out of position with the aid of a rope tied to the telehandler.

Once the old beam is on the ground, the new reclaimed piece of timber is lined up side by side and the slots for the struts and the king post marked out.  The new timber is then cut to length.

Once prepped, the timber is lifted onto the scaffold using the telehandler.  A rope is then tied to the middle of the timber and the other end onto the forks of the telehandler.  This allows the beam to be swung into position (which is not quite as easy as it sounds). Once in position, the wall is bricked up underneath the beam to hold it in place.  The temporary tie beam can then be removed. 

All in all, this took a couple of days to remove the old one, make a new one and install it.

One thing that Andy did say is that in the old days the carpenters would often put a coin in the bottom of the slot for one of the struts.  A sort of good luck charm.  We checked the old truss and there was no sign.  The coin must be in one of the other trusses!

The old tie beam (the one on the right) is used as a pattern for the new tie beam (the one of the left).

The old tie beam (the one on the right) is used as a pattern for the new tie beam (the one of the left).

Rather than having to take the entire roof apart, a temporary tie beam was installed while the old one was removed.

 

The original beam with the slot for the king post (below) and the new beam with a new slot.

The original beam with the slot for the king post (below) and the new beam with a new slot.

Lifting the tie beam into position using the telehandler

Lifting the tie beam into position using the telehandler

Lifting the tie beam over the scaffolding

Lifting the tie beam over the scaffolding

Tie a rope around it and lift it up in the air

Tie a rope around it and lift it up in the air

Pushing the timber into position a bit at a time

Pushing the timber into position a bit at a time

After all that hard work, the tie beam is finally in place. It matches the tie beams on the other trusses.

After all that hard work, the tie beam is finally in place. It matches the tie beams on the other trusses.

Chimneys removed

There were three chimneys on the property.  If you don’t believe me, check out the banner image at the top of this page!

One had not been used for 50 -60 years and we have decided to remove it entirely.  The middle chimney had been rendered at some point.  The roof timber around this chimney had rotted. so there had obviously been a problem at some point with this one.  This has been taken down and will be re-built in stone (as it was originally).  The third chimney was built of stone, but was a bit fragile.  With men working underneath it, we have taken the decision to take this one down to and rebuild it. 

Thus we will go from three chimneys to two, but at leasat they will match. 

There were three chimneys ornginally.  One is being completely removed as it is no longer used, the other two are being re-built.
There were three chimneys ornginally. One is being completely removed as it is no longer used (far left), the other two are being re-built (the middle and far right).

 

The stones from the old chimney have been cleaned and stacked on a pallet ready to go back up.

The stones from the old chimney have been cleaned and stacked on a pallet ready to go back up.

Demolishing another wall

One of the internal walls has had to come down. It already had a couple of bricked up doorways in it and trying to make two new doorways just introduced the risk that it was going to destabilise the wall.  The decision was taken earlier in the week to take it down and replace it with blockwork.  By Wednesday, the new wall had started to re-appear.  Fingers crossed, it will be finished this week.  While the wall is being re-built, the roof is being propped up.  This saves having to dismantle the roof, but it does look a little precarious.

The stone from the wall is very similar (if not identical) to the other internal wall that we had to remove last week.  It is likely that this stone will be reused on one of the internal walls in the kitchen (when that is built as part of phase 2).  So the mound of stone in the back field just grows bigger.

The start of a new wall between number 9 and number 10 - there were just too many alterations in the existing wall for it to be safe.

The start of a new wall between number 9 and number 10 – there were just too many alterations in the existing wall for it to be safe.

The new wall seen from the other direction.  Zep conducts his daily inspection of the building once the builders have gone home (looking for any leftover pasties!).  Note the tie beam on the king post truss in the background (the big beam running horizontally).  This is going to be replaced as part of the renovation.  The carpenter tells me that he thinks that this beam is original.

The new wall seen from the other direction. Zep conducts his daily inspection of the building once the builders have gone home (looking for any leftover pasties!). Note the tie beam on the king post truss in the background (the big beam running horizontally). This is going to be replaced as part of the renovation. The carpenter tells me that he thinks that this beam is original.

some of the best stone that we have found so far.  Fairly square and pretty regular.  We wll probably use this for the internal wall in the kitchen as part of the phase 2 build.

some of the best stone that we have found so far. Fairly square and pretty regular. We wll probably use this for the internal wall in the kitchen as part of the phase 2 build.

Replacing the purlins

The purlins are the pieces of timber that run horizontally from the end walls to the A frame truss that is in the middle of each of the properties.  Each cottage has 8 purlns – 4 each side of the truss.  Therefore, there are 24 in total.  Unfortunately, 6 need to be replaced – 4 were cracked and 2 were replacements (probably sometime in the last 50-60 years, but done poorly).

The first challenge is to find replacement timber.  This can be difficult as the woodwork is going to be exposed when the property is finished so it all needs to (sort of) match.  Given that the existing timbers are a bit “rough and ready”, we needed something similar.  The new timbers came from a reclamation yard in Preston (although the timbers themselves originated from France).

Using the old timbers as a pattern, the new timbers are cut to length and the end spigot cut to match the old.

Then it is a case of getting the new timber in place using the telehandler and fitting the timber.  The carpenter is taking all of this in his stride and we are getting 2 purlins replaced each day.

The next job will be to replace the tie beam (the bottom beam on the king post truss) in the middle cottage.  Fingers crossed and with some fine weather, this could happen towards the end of the week.

Then all the timber will be sandblasted and treated before the roof goes back on.

There are 24 purlins in total in the property.  Unfortunately, 6 of them had to be replaced.

There are 24 purlins in total in the property. Unfortunately, 6 of them had to be replaced.

Roof removed

In the last two days, the roof of the existing cottages has been removed.  Many of the stone slates were put onto pallets and lifted onto the ground using a telehandler – the remainder have been stacked on the scaffold.  There simply wasn’t enough room on the scaffold for all the slates.  I am amazed how quickly this has been done and all achieved in two days by 3 roofers.

With the roof removed, we can have a good look at the timbers and at first glance, they don’t appear to be too bad.  They are some that will need to be replaced, but we knew this before we started the work.  The architect is due this morning and some decisions will be taken then.

It looks pretty impressive from the outside, but even more impressive from the inside.

Here's the view from the rear of the property with the roof remvoed.

Here’s the view from the rear of the property with the roof remvoed.

Inside number 10 without the roof

Inside number 10 without the roof

This is the old kitchen (downstairs) and bathroom (upstairs) in number 10.  You can just see the king post truss in the top left corner for number 10, and through the upstairs doorway you can see the king post truss for number 9.

This is the old kitchen (downstairs) and bathroom (upstairs) in number 10. You can just see the king post truss in the top left corner for number 10, and through the upstairs doorway you can see the king post truss for number 9.

King post truss in number 9

King post truss in number 9

© 2024 Hagg Leys Farm

Theme by Anders NorenUp ↑