Work started this morning on putting the roof back on the existing building. By the end of the day all of the roofing felt and lathes will be on the building. This is a milestone since from this point onwards the building is no longer completely open to the elements.
It will take 7-10 days to get the roof completely finished, assuming there aren’t any problems.
You can also see the two rebuilt chimneys that now match – before the chimney on the left was smaller, rendered and had no string course. The chimneys, as the rest of the external masonry, has been sandblasted over the last weekend.

The two chimneys have been rebuilt and sandblasted. So too has the rear of the property. The felt and lathes are going on first to be followed by the stone slates.