The deadline for the tender process for Phase 1 was yesterday. 3 out of the 5 companies that we sent the tender documents to have responded. I am not sure if this is good or not, but the architect is trying to find out why two of the companies didn’t respond. All had previously expressed an interest in doing the work.
The good news is that the three tenders that we have received are all within 10% of one another.
The quantity surveyor is now looking through each of the responses to make sure that the three tenders are for the same work.