With the lower terrace now flagged, our attention has moved to the upper terrace.  This is considerably smaller, so will not take nearly as much time to get done.  Two days in and probably 60-70% of the upper terrace has been flagged.

Tomorrow the holes are going to be drilled for the lights to be installed in the garden.  While these are being drilled, Paddy and Jonny are going to flag the area under the front porch.  We will see considerable progress by the end of the week.

The upper terrace is significantly smaller than the lower terrace hence progress has been that bit quicker.  We will not be able to finish this area though until the stone arrives for the ashlar steps.  It could be another couple of weeks before that arrives.

The upper terrace is significantly smaller than the lower terrace hence progress has been that bit quicker. We will not be able to finish this area though until the stone arrives for the ashlar steps. It could be another couple of weeks before that arrives.