Month: June 2013 (Page 4 of 4)

Outbuilding gone…….

…..and the footings dug.  We need the building inspector to give it the OK tomorrow and then the footings will be laid on Friday.  Work will then start early next week rebuilding it, but this time with a proper cavity wall and a concrete slab floor (rather than flagstones laid directly onto the earth below).  It will be great to start building things rather than just knocking them down!  I can’t wait.

Walls removed and the footings dug ready for the concrete on Friday.

Walls removed and the footings dug ready for the concrete on Friday.

The walls now have been completely removed and the footings dug.  Once the wall has been built up to ground level, the soil and debris from the centre will be used to backfill the rest of the trench.

The walls now have been completely removed and the footings dug. Once the wall has been built up to ground level, the soil and debris from the centre will be used to backfill the rest of the trench.

Oops! We need to get this replaced, but we will reattach the plate to the wall once re-built as a temporary measure.

Oops! We need to get this replaced, but we will reattach the plate to the wall once re-built as a temporary measure. It used to be against the wall along the road.  When the wall was removed, so was this.

The stone from the outbuilding

The stone from the outbuilding

Roof removed

In the last two days, the roof of the existing cottages has been removed.  Many of the stone slates were put onto pallets and lifted onto the ground using a telehandler – the remainder have been stacked on the scaffold.  There simply wasn’t enough room on the scaffold for all the slates.  I am amazed how quickly this has been done and all achieved in two days by 3 roofers.

With the roof removed, we can have a good look at the timbers and at first glance, they don’t appear to be too bad.  They are some that will need to be replaced, but we knew this before we started the work.  The architect is due this morning and some decisions will be taken then.

It looks pretty impressive from the outside, but even more impressive from the inside.

Here's the view from the rear of the property with the roof remvoed.

Here’s the view from the rear of the property with the roof remvoed.

Inside number 10 without the roof

Inside number 10 without the roof

This is the old kitchen (downstairs) and bathroom (upstairs) in number 10.  You can just see the king post truss in the top left corner for number 10, and through the upstairs doorway you can see the king post truss for number 9.

This is the old kitchen (downstairs) and bathroom (upstairs) in number 10. You can just see the king post truss in the top left corner for number 10, and through the upstairs doorway you can see the king post truss for number 9.

King post truss in number 9

King post truss in number 9

Outbuilding almost gone

Well, the weather has been fantastic and the builders have really made some progress taking the outbuilding down at the end of the building.  With any luck  the new footings and floor will be exacavated tomorrow.  Within a few days, the rebuilding of this outbuilding will start.  This will be a real turning point as we start to put the building back together.

It has only taken the builders two days to get this far in demolishing the outbuilding at the end of the property.

It has only taken the builders two days to get this far in demolishing the outbuilding at the end of the property.

Outbuilding being demolished..

…to then be rebuilt.

Unfortunately, this is a single skin building with flagstones that are laid directly onto the soil.  As such, it is susceptible to damp and the only real solution is to take it down and rebuild it with a proper concrete floor and a cavity wall.  From the outside, it will look very similar to the building as it currently is, but it will be of a solid modern construction.  It will have been completely removed in the next two days.

At the end of day one, the roof has gone and the main roof timbers are exposed.  Work has already started on removing the stone work.  This is put onto pallets so they can be easily moved around the site.

This seems like a lot of trouble to go to for a quirky room on the end of the building, however, the 1788 map shows that this room was here back then.  So we would like to keep it in place. Longer term, it is going to be my office space.

The roof has been removed and the stones blocks are being removed one at a time.

The roof has been removed and the stones blocks are being removed one at a time.

View from the roof

The builders arrived last week and the scaffolding was completed over the weekend.  Before the work started (and while the builders weren’t around), we could not resist the temptation to have a look from the roof – the views are better than the roof itself!

There is now scaffolding right around the property to enable the roof to be removed.

There is now scaffolding right around the property to enable the roof to be removed.

 

Jo admiring the traditional stone slate roof!

Jo admiring the traditional stone slate roof!

 

The telehandler is used to reach up to roof level with a pallet.  This is then loaded with slates and brought down to ground level while the roof is being repaired.

The telehandler is used to reach up to roof level with a pallet. This is then loaded with slates and brought down to ground level while the roof is being repaired.

 

This is the front of the roof - all made from stone slates.  It has probably been re-roofed a number of times and this explains the varying qualtiy of the slates.  The slates are coursed so the bigger ones are at the bottom and the smaller ones are at the top.

This is the front of the roof – all made from stone slates. It has probably been re-roofed a number of times and this explains the varying qualtiy of the slates. The slates are coursed so the bigger ones are at the bottom and the smaller ones are at the top.

 

My pickup truck and a skip.  Question is which is which!

My pickup truck and a skip. Question is which is which!

 

This is the outbuilding (with new roof) and the newly installed polytunnel.  The orchard is behind.

This is the outbuilding (with new roof) and the newly installed polytunnel. The orchard is behind.

 

Dry stone walling – Day 25 & 26

The weather at the weekend was fantastic and we spent most of it working on the dry stone wall in the orchard.  By the end of the second day, another 5 metre section had been completed.  It is much quicker with two of us!

30.5m done.  17 to go. In the orchard anyway!

A weekend of fine weather sees another 5m section completed.  Allbeit, without the coping stones.

A weekend of fine weather sees another 5m section completed. Allbeit, without the coping stones.

Newer posts »

© 2025 Hagg Leys Farm

Theme by Anders NorenUp ↑