Author: stephen (Page 26 of 61)

Progress on the extension

Over the past 2-3 weeks, we have made significant progress on the extension.

The main roof beams are in, as are most of the roof spars.  Almost all of the ashlar stone surrounds are in place – particularly the really large pieces.  Most of the block work is up and the external stone work is catching up.  The roof will start to go on next week.  Exciting times.

Although the scaffolding obscures much of the new extension at the front, you can we the progress that has been made in the last couple of weeks.

Although the scaffolding obscures much of the new extension at the front, you can we the progress that has been made in the last couple of weeks.

Most of the roof spars are now in place.  There are a number of rooflight on this elevation and you can see where the gaps have been left in the roof timbers.

Most of the roof spars are now in place. There are a number of rooflight on this elevation and you can see where the gaps have been left in the roof timbers.

There is still quite a bit of stone work to go up on the end gable of the extension.  The roof beams sit on the inner blockwork and this is where we have concentrated our efforts.

There is still quite a bit of stone work to go up on the end gable of the extension. The roof beams sit on the inner blockwork and this is where we have concentrated our efforts.

The new doors have been installed in the existing cottages and the roof timbers are largely ready for the roof to go on (hopefully, next week).

The new doors have been installed in the existing cottages and the roof timbers are largely ready for the roof to go on (hopefully, next week).

This is the elevation faces into the sunken garden.  There are two sets of bifolding doors separated by a large square oak window.

This is the elevation faces into the sunken garden. There are two sets of bifolding doors separated by a large square oak window.

New basin for the bathroom

There is some good news and some bad news……

The new basin for the upstairs bathroom has arrived, but…….it is damaged.

It is a Stonekast sink made of limestone resin.  However, despite being well packed (in a cardboard box that was in a wooden create), it still arrived damaged.  Ho hum.

It is a great looking sink (I just love the shape and texture) and we have ordered a bath to match (this is due to arrive later in the month), but we are just going to have to wait for another one to be dispatched.

OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA

Progress on the extension roof

We have had a couple of fine days already this week and that means that most of the roof spars have been installed.  This is a bit of a slow job since there are so many rooflights – standard patent glazing in the lounge and kitchen (together with electric openers) and pairs of Veluxes elsewhere.  There are a total of 6 pairs of Velux windows to be installed throughout the extension.

More of the roof joists have been installed.  There is still quite a bit of work to do around the rooflights - you can see the gap in the roof spars about the lounge roof.

More of the roof joists have been installed. There is still quite a bit of work to do around the rooflights – you can see the gap in the roof spars about the lounge roof.

The hearth in the lounge

We are trying to sort out the arrangement of the hearth in the lounge.  We need to settle on an arrangement fairly quickly as the roof starts to go on next and we need to know where the flue is going to go.

The challenge here is that this end wall is very tall.

We are considering internal windows from the lounge into the master bedroom – high up so privacy isn’t an issue, but it does connect the master bedroom with the other spaces.

We are also looking at corner log stoves (although not shown in these pictures).

While this arrangement isn’t exactly right yet, we are starting to get there (I think!).

20131112 hearth view 41 20131112 hearth view 3 20131112 hearth view 1 20131112 hearth view 2

Getting the new stonework into position

There is a large square picture window in the new extension.  It is big.  Very picture.  You step up into it to get from the lounge into the master bedroom.

The ashlar blocks (three of them) that form the window will were heavy enough.  But the ashlar jambs (the bits that go up the sides) are enormous and weigh in at 640kgs – far too heavy to be lifted by hand.  But to use a crane, you have to be able to attach (safely) the stone to the lifting hook.  The builders had a metal plate made with an eyelet.  This was then bolted and glued to the back of the stone work.  This allowed the stone to be attached without leaving any marks on the outside faces.

There were smiles around once these pieces reach their final resting place.

The large pieces of ashlar are on the telehandler lying on their backs.  The crane will lift these up one by one using the metal plate that has been fixed to the back of the stone.

The large pieces of ashlar are on the telehandler lying on their backs. The crane will lift these up one by one using the metal plate that has been fixed to the back of the stone.

A metal plate with an eyelet has been bolted and glued to the back of the stone.  This will be left in place as it is behind all the stonework and will not be seen.

A metal plate with an eyelet has been bolted and glued to the back of the stone. This will be left in place as it is behind all the stonework and will not be seen.

Once roughly in position, the column is nudged into it's final location while most of the weight is still being held by the crane.  No one wants this to topple over as they will be no stopping it once it starts to go.

Once roughly in position, the column is nudged into it’s final location while most of the weight is still being held by the crane. No one wants this to topple over as they will be no stopping it once it starts to go.

This peices of ashlar weigh in at around 640kgs (according to the crane operator).  They are far too heavy to be lifted by hand and they are still a challenge even with a crane to get into exact position.

This peices of ashlar weigh in at around 640kgs (according to the crane operator). They are far too heavy to be lifted by hand and they are still a challenge even with a crane to get into exact position.

The head is fairly easy to get into position with a couple of straps around it.

The head is fairly easy to get into position with a couple of straps around it.

 

 

Progress on the extension

We are now starting to put the spars on the roof.   If the weather is kind to us this week, we should be able to get going on the roof next week.  It will be good to get this part of the building watertight as the inside is like a paddling pool!  And that is not to mention the mud!

Tomorrow we have a crane arriving to help position some of the larger pieces of ashlar.  It will be good to see these in position.

All of the main roof beams are in and we are now putting in the spars.  This will enable us to start to get the roof on next week.

All of the main roof beams are in and we are now putting in the spars. This will enable us to start to get the roof on next week.

 

 

Rear doors

Both pairs of rear doors have now been installed.  They are big and let a lot of light into the building.  It is good to have the temporary boarding removed.  It gives a much better impression of what these rooms will be like when finished.

They are 2 locks on each door, so a total of 8 across all of the doors.  The joinery arranged for the locks to be “suited” so the same key is used on all 8 locks. It just makes life a lot easier!

The second pair of rear doors were installed yesterday.  The doors on the left are into the snug and the doors on the right are into the hall.

The second pair of rear doors were installed yesterday. The doors on the left are into the snug and the doors on the right are into the hall.

This is the view from inside the hall.  There is now a lot light inside the hall.

This is the view from inside the hall. There is now a lot light inside the hall.

The steel post between the two doors will be covered in plasterboard and then plastered.

The steel post between the two doors will be covered in plasterboard and then plastered.

Roof truss detail

Most of the oak beams are now in place in the roof of the extension.  There is still some work to be done on the valleys (where the two roofs of the extension meet).  However, there was a bit of confusion about how this was meant to be built.  The upshot was that a piece of oak timber was missed off the order and we now need to wait for it to be delivered next week. 

In the meantime, we have pushed ahead with adding the spars to the rest of the roof.

Just in case you thought it was easy to build a roof!  All of these peices of oak are cut by hand and manhandled into position.  This drawing makes it look too easy!

Just in case you thought it was easy to build a roof! All of these peices of oak are cut by hand and manhandled into position. This drawing makes it look too easy!

There is a temporary prop in place, but this is looking very similar to the 3D roof truss detail.  The purlins for the valleys are currently missing.

There is a temporary prop in place, but this is looking very similar to the 3D roof truss detail. The purlins for the valleys are currently missing.

All the main beams are now in place and work has started on installing the spars.  Hopefully, by the middle of next week, the roof will be on.

All the main beams are now in place and work has started on installing the spars. Hopefully, by the middle of next week, the roof will be on.

New doors installed in the rear of the cottage

The first pair of doors has been installed in the rear of the existing cottages.  Now the temporary boardings have been removed and the new doors installed, there is a lot more light inside.

The second pair of doors will be installed tomorrow.

One pair of rear doors fitted in the existing cottages.  You can also see the progress on the roof trusses in the new extension.

One pair of rear doors fitted in the existing cottages. You can also see the progress on the roof trusses in the new extension.

The new rear doors really do let a lot of light into the building.  The second pair of doors will be installed on Friday.

The new rear doors really do let a lot of light into the building. The second pair of doors will be installed on Friday.

Progress on the roof

I have been on a course this week (the Loxone training course – more later) which has meant that I haven’t been on site much.  With so much going on, it is a meant of a shame not to be here, but the training course has been a welcome break.  I do go first thing in the morning (once it is light!).  There is little point in going in the evenings as it is dark by the time I get back.

This week the builders have been concentrating on getting the roof up with the hope that we can get it covered over early next week.  However, it is a constant battle with the weather at the moment.  Even so, they are making good progress.

The roof is relatively complex as you can see from the architects diagram and notes.  However, it all seems to be going according to plan.

All three trusses are now in position.  The purlins between the trusses have been installed and the “free ends” have been propped up in position while the blockwork is built up to support them.  Hopefully all the major woodwork for the roof will be in place by the end of the week.

Just in case you thought it was easy to build a roof!  All of these peices of oak are cut by hand and manhandled into position.  This drawing makes it look too easy!

Just in case you thought it was easy to build a roof! All of these peices of oak are cut by hand and manhandled into position. This drawing makes it look too easy!

This is first thing in the morning before I go off to my Loxone training course.  You can see all of the three trusses are now in position - 2 running one way and a third (in the kitchen) running at 90 degrees.

This is first thing in the morning before I go off to my Loxone training course. You can see all of the three trusses are now in position – 2 running one way and a third (in the kitchen) running at 90 degrees.

The majority of the beams went in yesterday.  Today the builders have been concentrating on building up the blockwork to support the ends of the beams.  You can see in this photo that some of the beams (look to camera right) are propped up at the moment waiting for the blockwork to be built up around them.

The majority of the beams went in yesterday. Today the builders have been concentrating on building up the blockwork to support the ends of the beams. You can see in this photo that some of the beams (look to camera right) are propped up at the moment waiting for the blockwork to be built up around them.

« Older posts Newer posts »

© 2025 Hagg Leys Farm

Theme by Anders NorenUp ↑