We are starting to finish off some of the jobs that have been hanging around for a while. One of them is the utility room. We have been using this room for a while, but it has just housed the washing machine and the dryer. Today, we started on installing a couple of cupboards and a work surface. We have bothered with an expensive range of units – this is a utility room after all! But we have picked units and worksurfaces to match the rest of the house.
Author: stephen (Page 6 of 61)
We have had some snow already this winter, but this morning we had around 3 inches. This was enough to stop the traffic for a while and it was eerily quiet for a while.
These photos are courtesy of Paddy Martin who did the work in the garden. These before and after shots just show how much work has gone into sorting out the sunken garden.

Here is the before and after for the sunken garden. All in all, it took about 8 weeks to sort this out.
At last all of the ashlar is in place and all of the flagstones are down. There is still pointing to do, but that is going to have to wait a bit until the weather improves – it can’t be too wet or too cold when doing the pointing.

Three sets of steps and 160 square meters of flagstones. The pointing is still to be done between the flagstones, but we are going to have to wait for some better weather. The lights are still to be installed (although the holes and wiring have been put in place).

We still have to point the flagstones. This will be done using lime pointing (just like the main house), however, this is going to have to wait for better weather.
There was major relief today when the final set of stone steps were installed in the garden. Installing these steps has been a monumental effort on behalf of Paddy and Jonny. Most of the stones are well over safe working loads for two men, so that have had to use the ingenuity to get these in without any major incidents.

Once the step is roughly in position (but still resting on the slabs of insulation), the stone step is lifted up (the sides are protected by some thin blue foam) and the insulation removed (very quickly). If it all works out properly, the stone step ends up in the right spot!
After 5 weeks of waiting, the ashlar finally arrived for the stone steps in the sunken garden. We need to get the steps into position so that we can flag up against them and get the flagging finished.

We are installing the three large ashlar slabs that are laid in front of the bi-folding doors to the lounge. This makes the top step wide enough so that the doors can be opened without overhanging the top step.

There are lights to be installed in each of these three slabs (you can see the wiring where the middle slab is still to be laid. These slabs are being moved into position using a powerful suction device.
The weather this week hasn’t been great. And the weather today has been great either. The fog never really lifted at all. However, we are continuing to make progress in the sunken garden and it is starting to feel like we have turned a corner. The main thing that is holding us up now is the delivery of the stone steps from the quarry. This was meant to take 4-5 weeks, but we are now on week 6. I am guessing that by the middle of next week that we may run out of things to do if the stone doesn’t arrive.

The last of the has been completed so that the flagstones can be laid on the upper terrace. This small wall can’t be seen (it is under the hessian) as it is being protected from the wet weather that we have had today. We have also had the holes drilled to take the lights in both the lower and upper terraces.

The wall that we have built today is hidden under the hessian. There is still some work to be done on the other side of the wall, but that will have to wait until tomorrow. Hopefully, the weather will be a little bit better! Or rather drier!

A view from above showing one of the 92mm holes that have drilled in the flagstones to take the lights. The wires were laid a few weeks ago before we put down the crushed stone. We worked out that these lights need to be about 300mm away from the wall to create the best effect.
With the lower terrace now flagged, our attention has moved to the upper terrace. This is considerably smaller, so will not take nearly as much time to get done. Two days in and probably 60-70% of the upper terrace has been flagged.
Tomorrow the holes are going to be drilled for the lights to be installed in the garden. While these are being drilled, Paddy and Jonny are going to flag the area under the front porch. We will see considerable progress by the end of the week.
After the demise of our last weather station last week, we have installed a new one. It is remarkable similar to our previous weather station, however, this does have a solar meter which measures daylight. Our previous weatherstation was a Weathereye-WEA22. The new one is a Aercus WS3083.
This one simply plugged into the same PC (via USB) as the old station and it worked. I had to tell it that it now had a Solar meter, but that was about the only change. The data is uploaded to the website every 15 minutes and you can access the page from here: http://www.haggleysfarm.co.uk/weather.

It looks very similar to the old one, except this one is well screwed onto the shed. Although it is a different make, the outdoor attachments are identical (except this unit has a solar meter). It simply plugged into the PC and started uploading data. It took no more than 60 minutes to assemble and set up.
























