Category: garden (Page 2 of 6)

More progress in the sunken garden

After 5 weeks of waiting, the ashlar finally arrived for the stone steps in the sunken garden.  We need to get the steps into position so that we can flag up against them and get the flagging finished.

We are installing the three large ashlar slabs that are laid in front of the bi-folding doors to the lounge.  This makes the top step wide enough so that the doors can be opened without overhanging the top step.

We are installing the three large ashlar slabs that are laid in front of the bi-folding doors to the lounge. This makes the top step wide enough so that the doors can be opened without overhanging the top step.

There are lights to be installed in each of these three slabs (you can see the wiring where the middle slab is still to be laid.  These slabs are being moved into position using a powerful suction device.

There are lights to be installed in each of these three slabs (you can see the wiring where the middle slab is still to be laid. These slabs are being moved into position using a powerful suction device.

Using a powerful suction device, the final ashlar slab is lifted into position.  These slabs are very heavy and this photo doesn't really convey exactly how difficult this task was.  There was relief all round once it was in position.

Using a powerful suction device, the final ashlar slab is lifted into position. These slabs are very heavy and this photo doesn’t really convey exactly how difficult this task was. There was relief all round once it was in position.

These steps still need to be pointed, but the steps are pretty much complete.  They also need to be pressure washed to get the "green" of them - they have been covered for the past few weeks to protect them. Once cleaned, the steps will match the new slabs installed in front of the doors.

These steps still need to be pointed, but the steps are pretty much complete. They also need to be pressure washed to get the “green” of them – they have been covered for the past few weeks to protect them. Once cleaned, the steps will match the new slabs installed in front of the doors.

Home straight with the sunken garden

The weather this week hasn’t been great.  And the weather today has been great either.  The fog never really lifted at all.  However, we are continuing to make progress in the sunken garden and it is starting to feel like we have turned a corner.  The main thing that is holding us up now is the delivery of the stone steps from the quarry.  This was meant to take 4-5 weeks, but we are now on week 6.  I am guessing that by the middle of next week that we may run out of things to do if the stone doesn’t arrive.

The last of the has been completed so that the flagstones can be laid on the upper terrace.  This small wall can't be seen (it is under the hessian) as it is being protected from the wet weather that we have had today.  We have also had the holes drilled to take the lights in both the lower and upper terraces.

The last of the has been completed so that the flagstones can be laid on the upper terrace. This small wall can’t be seen (it is under the hessian) as it is being protected from the wet weather that we have had today. We have also had the holes drilled to take the lights in both the lower and upper terraces.

The wall that we have built today is hidden under the hessian.  There is still some work to be done on the other side of the wall, but that will have to wait until tomorrow.  Hopefully, the weather will be a little bit better!  Or rather drier!

The wall that we have built today is hidden under the hessian. There is still some work to be done on the other side of the wall, but that will have to wait until tomorrow. Hopefully, the weather will be a little bit better! Or rather drier!

A view from above showing one of the 92mm holes that have drilled in the flagstones to take the lights.  The wires were laid a few weeks ago before we put down the crushed stone.  We worked out that these lights need to be about 300mm away from the wall to create the best effect.

A view from above showing one of the 92mm holes that have drilled in the flagstones to take the lights. The wires were laid a few weeks ago before we put down the crushed stone. We worked out that these lights need to be about 300mm away from the wall to create the best effect.

There was a small area, just behind the smaller of the front gates, that needed to be flagged.  This was completed this week.

There was a small area, just behind the smaller of the front gates, that needed to be flagged. This was completed this week.

As well as sorting out the flagstones to the rear of the property we have also sorted out the flagstones under the porch canopy.  They still need to be pointed, but the pointing will be done when all of the flagstones - front and back - have been laid.

As well as sorting out the flagstones to the rear of the property we have also sorted out the flagstones under the porch canopy. They still need to be pointed, but the pointing will be done when all of the flagstones – front and back – have been laid.

More progress in the sunken garden

With the lower terrace now flagged, our attention has moved to the upper terrace.  This is considerably smaller, so will not take nearly as much time to get done.  Two days in and probably 60-70% of the upper terrace has been flagged.

Tomorrow the holes are going to be drilled for the lights to be installed in the garden.  While these are being drilled, Paddy and Jonny are going to flag the area under the front porch.  We will see considerable progress by the end of the week.

The upper terrace is significantly smaller than the lower terrace hence progress has been that bit quicker.  We will not be able to finish this area though until the stone arrives for the ashlar steps.  It could be another couple of weeks before that arrives.

The upper terrace is significantly smaller than the lower terrace hence progress has been that bit quicker. We will not be able to finish this area though until the stone arrives for the ashlar steps. It could be another couple of weeks before that arrives.

Flagging the lower terrace

The majority of the flagstones have been laid in the lower terrace.  They still need to be pointed  as well as the holes drilled for the lights and the ashlar steps installed.  Things are being held up a little bit by the weather as well as the availability of the stone steps (the local quarry is very busy!).

The flagstones gently slop away from the house and any rainwater is connected by a drain that runs along the back of this area (you can just see the slot (protected by a yellow strip) to camera right).  There are a couple of flagstones that are propped up against the wall.  These need to be drilled to take the uplighters that will be installed later.

The flagstones gently slop away from the house and any rainwater is connected by a drain that runs along the back of this area (you can just see the slot (protected by a yellow strip) to camera right). There are a couple of flagstones that are propped up against the wall. These need to be drilled to take the uplighters that will be installed later.

The flagstones have now been laid in the lower terrace in the sunken garden.  The holes for the uplighters will be drilled next week and we should then be able to get all the flags laid in this area.  We are going to use a special epoxy compound for the pointing, but this will be done when all of the flags have been laid.

The flagstones have now been laid in the lower terrace in the sunken garden. The holes for the uplighters will be drilled next week and we should then be able to get all the flags laid in this area. We are going to use a special epoxy compound for the pointing, but this will be done when all of the flags have been laid.

Lower terrace

 

Progress in the sunken garden

We made some good progress in the sunken garden last week.  Or rather Paddy and Jonny made some good progress.  It did rain on a couple of the days, but not until late in the afternoon so it didn’t hamper progress too much last week.

This weekend was down to us to get as much work done on the reclaimed wall that separate the lower and upper terraces.  By the end of the weekend, we had all but finished this section of wall.  We ran out of stone (but there is a lot in the back field), but there is probably only a couple of hours of work left here.  All in all, it was a good couple of days of walling.  And in some nice weather too!

There is probably still a couple of days work for Paddy and Jonny to do to finish off the flags in the lower terrace.  In the meantime, we have continued to work on the reclaimed wall that separates the two.  This is built in a similar way to other walls in the garden.

There is probably still a couple of days work for Paddy and Jonny to do to finish off the flags in the lower terrace. In the meantime, we have continued to work on the reclaimed wall that separates the two. This is built in a similar way to other walls in the garden.

With more of the wall complete, we are now ready to turn the corners on each of the ends.  There will be two sets of stone steps here.

With more of the wall complete, we are now ready to turn the corners on each of the ends. There will be two sets of stone steps here.

The wall is now the same height as the other walls that we built in the garden.  We have turned the corner and a set of stone steps will sit on the concrete blockwork.  We will need to wait for another 2-3 weeks for the stonework to arrive.

The wall is now the same height as the other walls that we built in the garden. We have turned the corner and a set of stone steps will sit on the concrete blockwork. We will need to wait for another 2-3 weeks for the stonework to arrive.

The view from the other end of this section of wall.  We have run out of stone (we have lots in the back field, we just need to find it) to finish the rear part of this wall.  It will have to wait until next weekend.

The view from the other end of this section of wall. We have run out of stone (we have lots in the back field, we just need to find it) to finish the rear part of this wall. It will have to wait until next weekend.

Progress in the sunken garden

The weather has hampered our efforts this week, but even so we are making progress.  After 2 days of laying flagstones, Paddy and Jonny reckon that that have laid about 20 sq yards (this is out of a total of about 160 sq  yards, so there is still a way to go!).  We reckon that it will take most of the coming week (weather permitting) to get all of the flagstones laid just on the lower terrace.  However, you can see from the flags that have been laid so far that it is going to look amazing when it is finished.

Jo and I have started on the wall that is between the two sets of steps that divides the upper and lower terraces.  This wall needs to be brought up to about 300mm to allow Paddy and Jonny to lay the flags up to it.  The rest of the wall can be finished off at a later date, but the bottom few courses need to be in place for them early next week.  I am glad to say that by the end of the day we had succeeded in building up the wall for them.  It is deceptive, but there is a pickup full of reclaimed stone just in the short little wall (it might be short, but it is quite long!).

The blue pipes allow any water that builds up behind the retaining wall to escape.  This blue pipes will be cut short and plastic weep holes built into the wall at the front to allow the water to escape should it build up.

End of day 2 laying flagstones and we reckon that about 20 sq yards has been laid.  A rough calculation would seem to indicate that it will take most of the coming week to get all of the flagstones laid on the lower part of the sunken garden.

End of day 2 laying flagstones and we reckon that about 20 sq yards has been laid. A rough calculation would seem to indicate that it will take most of the coming week to get all of the flagstones laid on the lower part of the sunken garden.

Two days in and Paddy and Jonny have laid about 20 sq yards of flagstones.  By the end of the coming week, the lower terrace should be finished (in terms of laying the flagstones).

Two days in and Paddy and Jonny have laid about 20 sq yards of flagstones. By the end of the coming week, the lower terrace should be finished (in terms of laying the flagstones).

This is before we started building the wall at the front of the retaining wall.  The blue pipes allow any water that builds up to drain through the front wall.  The wiring has been installed for the two lights that will be at the front and the drain has been installed to allow the water to run off the flagstones once they are laid.

This is before we started building the wall at the front of the retaining wall. The blue pipes allow any water that builds up to drain through the front wall. The wiring has been installed for the two lights that will be at the front and the drain has been installed to allow the water to run off the flagstones once they are laid.

We need to get this part of the reclaimed wall built so that the flagstones can be laid throughout the lower terrace of the sunken garden.  This took about half a day to get to this level and this is high enough to allow Paddy and Jonny to finishing flagging this area.  We will be able to finish off this wall after the flags have been laid.  The blue pipes will be cut shorter and will feed into plastic weep holes built into this wall.

We need to get this part of the reclaimed wall built so that the flagstones can be laid throughout the lower terrace of the sunken garden. This took about half a day to get to this level and this is high enough to allow Paddy and Jonny to finishing flagging this area. We will be able to finish off this wall after the flags have been laid. The blue pipes will be cut shorter and will feed into plastic weep holes built into this wall.

There are two sets of stone steps to be installed at each end of this lower wall.  We have formed the steps in blockwork and the large pieces of ashlar will be bedded onto the concrete blockwork.  Unfortunately, the stone is not due to arrive for another 4 or 5 weeks.  In the meantime, we are going to have to get on with the rest of the work.

There are two sets of stone steps to be installed at each end of this lower wall. We have formed the steps in blockwork and the large pieces of ashlar will be bedded onto the concrete blockwork. Unfortunately, the stone is not due to arrive for another 4 or 5 weeks. In the meantime, we are going to have to get on with the rest of the work.

The wall between the two sets of stone steps is being built in the same way as the other walls in the sunken garden.  The stone has been reclaimed from other parts of the property - the majority of this stone came from a wall that we knocked down in one of the old cottages.  Most of this stone went into the wall in the kitchen, but this stone was left over.

The wall between the two sets of stone steps is being built in the same way as the other walls in the sunken garden. The stone has been reclaimed from other parts of the property – the majority of this stone came from a wall that we knocked down in one of the old cottages. Most of this stone went into the wall in the kitchen, but this stone was left over.

 

First of the flagstones being installed

While we were away for a couple of days this week, the first of the flagstones has been installed in the sunken garden.  It is going to take quite some time to get all of these laid.  Still, it will look great once it is done.

The first of the flagstones are starting to be laid in the lower terrace of the sunken garden.  We are using a random pattern rather than laying the flagstones in courses. The flags are of varying thicknesses and we are coping with this by using a thick bed of sand and cement underneath the flags.

The first of the flagstones are starting to be laid in the lower terrace of the sunken garden. We are using a random pattern rather than laying the flagstones in courses. The flags are of varying thicknesses and we are coping with this by using a thick bed of sand and cement underneath the flags.

The thicker of the flagstones are probably on the weight limit for two men to carry - you certainly don't want to have to move them far.  Fortunately, we have managed to move the pallets into the sunken garden using the telehandler.

The thicker of the flagstones are probably on the weight limit for two men to carry – you certainly don’t want to have to move them far. Fortunately, we have managed to move the pallets into the sunken garden using the telehandler.

The flags are of varying quality, but this all adds to the rustic feel of this space.  The worst of the flagstones we are putting to one side and will return the reclamation yard for them to be replaced - they are so rough, they are a "trip hazard"!

The flags are of varying quality, but this all adds to the rustic feel of this space. The worst of the flagstones we are putting to one side and will return the reclamation yard for them to be replaced – they are so rough, they are a “trip hazard”!

Sunken garden and the weather

The bad weather, which has been forecast for a while now, hit us today.  By 2pm, it was too wet to carry on, but Paddy and Jonny did their best.  They switched their attentions to the step by the back door and this has now be laid.  There is no point in trying to point it in this weather, but at least the flagstones are down.  Their is a step to go in underneath the porch and this is being earmarked for another “wet day activity”.  We can’t really do them both at the same time otherwise you wouldn’t be able to get in the house!

Before the really bad weather hit, we had time to use the wacker plate to pack down the crushed stone in the sunken garden.  Now the stone has been packed down, we need to put some more crushed stone to bring the levels back up to where they should be.

Before the really bad weather hit, we had time to use the wacker plate to pack down the crushed stone in the sunken garden. Now the stone has been packed down, we need to put some more crushed stone to bring the levels back up to where they should be.

The upper terrace still has to be levelled, but we are taking the opportunity to get rid of some of the waste stone behind the retaining wall.

The upper terrace still has to be levelled, but we are taking the opportunity to get rid of some of the waste stone behind the retaining wall.

The temporary concrete blocks and flagstone have been removed to make way for some concrete and some new (or rather old) flagstones to be installed.

The temporary concrete blocks and flagstone have been removed to make way for some concrete and some new (or rather old) flagstones to be installed.

These still need to be pointed, but it makes a huge difference to the appearance of this area.  The shoe on the bottom of the rainwater pipe also needs a coat of black paint!

These still need to be pointed, but it makes a huge difference to the appearance of this area. The shoe on the bottom of the rainwater pipe also needs a coat of black paint!

This area is starting to look a little more finished.  It is amazing how you can get used to things looking half finished!!  I have spent the last 2 years doing so!

This area is starting to look a little more finished. It is amazing how you can get used to things looking half finished!! I have spent the last 2 years doing so!

 

Progress on the sunken garden

It has been very wet here in Yorkshire for the past week and this has impacted on the progress on the work in the garden.  Actually, the progress has been pretty good, but the impact is definitely starting to show on the grass!  Lots of rain, new grass and heavy machinery are not a great combination.  Still, it will grow back!

Paddy and Jonny have really put the hours in this week and it shows.  The two terraces are starting to take shape and next week we should be in a position to start laying the first of the flagstones.  All of the wiring is now in place for the uplighters that will light up the walls around the garden at night.

There are a number of uplighters around the perimeter of both the lower and upper terraces.  The wiring has to be put in place before the flagstones are laid.  We know the position of the lights so that we can drill the holes after the flagstones have been laid.

There are a number of uplighters around the perimeter of both the lower and upper terraces. The wiring has to be put in place before the flagstones are laid. We know the position of the lights so that we can drill the holes after the flagstones have been laid.

The wires coming out of the short sections of brown drainage pipe are for the lights that are going to be recessed into the flagstones.  The lights are positioned 30cms from the walls to shine light up against the stone work.

The wires coming out of the short sections of brown drainage pipe are for the lights that are going to be recessed into the flagstones. The lights are positioned 30cms from the walls to shine light up against the stone work.

The blue pipes allow water that builds up behind the retaining wall to seep through the stonework that will face this retaining wall.  The pipes will feed into small plastic weep holes in the finished wall.

The blue pipes allow water that builds up behind the retaining wall to seep through the stonework that will face this retaining wall. The pipes will feed into small plastic weep holes in the finished wall.

This blockwork has been built to support the stone steps that will be installed here.  The blockwork to the right will be face with the same stone as you can see on the back wall above.

This blockwork has been built to support the stone steps that will be installed here. The blockwork to the right will be face with the same stone as you can see on the back wall above.

These arrived in the week on 4 lorries.  There should be enough flagstones here to cover the 154 sqm in the sunken garden.  It is difficult to believe that we are going to need this many flagstones, but we did measure it (at least twice!).  As well as the sunken garden, there are also a couple of areas to flag at the front of the property.

These arrived in the week on 4 lorries. There should be enough flagstones here to cover the 154 sqm in the sunken garden. It is difficult to believe that we are going to need this many flagstones, but we did measure it (at least twice!). As well as the sunken garden, there are also a couple of areas to flag at the front of the property.

There is a drainage channel along the back of the sunken garden.  The flagstones are laid so that water will run away from the house and into this channel.  Only the thing plastic groove will be seen as the rest will be covered by flagstones.

There is a drainage channel along the back of the sunken garden. The flagstones are laid so that water will run away from the house and into this channel. Only the thing plastic groove will be seen as the rest will be covered by flagstones.

 

Sunken garden

Work continues in the sunken garden despite the rain.  We are hopefully that we will have the levels sorted out in the two parts of the sunken garden by the end of the week.  However, the first thing that we need to do is to build the retaining wall between the two terraces.

This is the retaining wall that will separate the lower and the upper terrace in the sunken garden.  It has rained throughout the day today and this makes progress slow.  And very muddy!

This is the retaining wall that will separate the lower and the upper terrace in the sunken garden. It has rained throughout the day today and this makes progress slow. And very muddy!

« Older posts Newer posts »

© 2024 Hagg Leys Farm

Theme by Anders NorenUp ↑