We have just had the first dump of snow this winter and the views are amazing. It is the time of year that you are glad of 4×4’s.
Category: Gardening (Page 3 of 9)
All things to do with gardening
These photos are courtesy of Paddy Martin who did the work in the garden. These before and after shots just show how much work has gone into sorting out the sunken garden.
At last all of the ashlar is in place and all of the flagstones are down. There is still pointing to do, but that is going to have to wait a bit until the weather improves – it can’t be too wet or too cold when doing the pointing.
There was major relief today when the final set of stone steps were installed in the garden. Installing these steps has been a monumental effort on behalf of Paddy and Jonny. Most of the stones are well over safe working loads for two men, so that have had to use the ingenuity to get these in without any major incidents.
After 5 weeks of waiting, the ashlar finally arrived for the stone steps in the sunken garden. We need to get the steps into position so that we can flag up against them and get the flagging finished.
The weather this week hasn’t been great. And the weather today has been great either. The fog never really lifted at all. However, we are continuing to make progress in the sunken garden and it is starting to feel like we have turned a corner. The main thing that is holding us up now is the delivery of the stone steps from the quarry. This was meant to take 4-5 weeks, but we are now on week 6. I am guessing that by the middle of next week that we may run out of things to do if the stone doesn’t arrive.
With the lower terrace now flagged, our attention has moved to the upper terrace. This is considerably smaller, so will not take nearly as much time to get done. Two days in and probably 60-70% of the upper terrace has been flagged.
Tomorrow the holes are going to be drilled for the lights to be installed in the garden. While these are being drilled, Paddy and Jonny are going to flag the area under the front porch. We will see considerable progress by the end of the week.
The majority of the flagstones have been laid in the lower terrace. They still need to be pointed as well as the holes drilled for the lights and the ashlar steps installed. Things are being held up a little bit by the weather as well as the availability of the stone steps (the local quarry is very busy!).
We made some good progress in the sunken garden last week. Or rather Paddy and Jonny made some good progress. It did rain on a couple of the days, but not until late in the afternoon so it didn’t hamper progress too much last week.
This weekend was down to us to get as much work done on the reclaimed wall that separate the lower and upper terraces. By the end of the weekend, we had all but finished this section of wall. We ran out of stone (but there is a lot in the back field), but there is probably only a couple of hours of work left here. All in all, it was a good couple of days of walling. And in some nice weather too!
The weather has hampered our efforts this week, but even so we are making progress. After 2 days of laying flagstones, Paddy and Jonny reckon that that have laid about 20 sq yards (this is out of a total of about 160 sq yards, so there is still a way to go!). We reckon that it will take most of the coming week (weather permitting) to get all of the flagstones laid just on the lower terrace. However, you can see from the flags that have been laid so far that it is going to look amazing when it is finished.
Jo and I have started on the wall that is between the two sets of steps that divides the upper and lower terraces. This wall needs to be brought up to about 300mm to allow Paddy and Jonny to lay the flags up to it. The rest of the wall can be finished off at a later date, but the bottom few courses need to be in place for them early next week. I am glad to say that by the end of the day we had succeeded in building up the wall for them. It is deceptive, but there is a pickup full of reclaimed stone just in the short little wall (it might be short, but it is quite long!).
The blue pipes allow any water that builds up behind the retaining wall to escape. This blue pipes will be cut short and plastic weep holes built into the wall at the front to allow the water to escape should it build up.